Timescales and locations
The multi-storey improvement programme is expected to take around ten years to complete and the work for each block will be split into two phases:
- Phase 1, design and development - surveys, plans and designs for the block
- Phase 2, construction work - improvement works begin on site.
Phase 1 - design and development
| 2023 - 2025 | 2025 - 2027 | 2027 - 2029 | 2029 - 2031 | 2031 - 2033 |
|
Craigmillar Court Inchmickery Court Oxcars Court Peffermill Court
|
Cables Wynd House Castleview House Forteviot House Little France House Linksview House Marytree House Moredun House Moncrieffe House |
Citadel Court Inchcolm Court Inchgarvie Court Kirkgate House Persevere Court |
Cobbinshaw House Drover's Bank Dunsyre House Kilncroft Medwin House Midcairn |
Future blocks to be determined |
Phase 2 - construction work
| 2023 - 2025 | 2025 - 2027 | 2027 - 2029 | 2029 - 2031 | 2031 - 2033 |
|
May Court Gunnet Court |
Craigmillar Court Inchmickery Court Oxcars Court Peffermill Court |
Cables Wynd House Castleview House Forteviot House Linksview House Little France House Marytree House Moredun House Moncrieffe House |
Citadel Court Inchcolm Court Inchgarvie Court Kirkgate House Persevere Court
|
Cobbinshaw House Dunsyre House Drover's Bank Kilncroft Medwin House Midcairn |